A bespoke Activated Carbon Vessel System has recently been supplied to Thames Water as part of a system to remove impurities from anaerobic digester gases. Not only did the system meet the stringent clean up requirements at Thames Water, but it also offers zero plant shut down when carrying out routine vessel maintenance. 

Removing impurities from waste water
Providing the population with clean drinking water is a dirty job. Many processes need to be implemented to remove impurities from waste water. These processes need to meet stringent compliance regulations to guarantee the production of safe drinking water. One of these processes uses anaerobic digestion, the by-product of which is biogas. The biogas can be used as a valuable source of fuel, provided it is ‘sweetened’ by removal of the trace amount of contaminants it contains.

Delivering modern filtration
Activated carbon granules or pellets are used for the removal of hydrogen sulphide (H2S) in biogas streams generated from various sources such as landfills, anaerobic digesters or, as in this application, municipal wastewater treatment plants. A granular form of activated carbon, a material containing highly porous carbon particles, is stored in specially designed vessels. When a biogas stream is passed through the vessel, H2S and other impurities such as siloxanes are removed.

Having recently designed and built two smaller systems to achieve H2S removal for another UK water company, ThermTech was approached by CC Jensen, a project management contractor to the water industry. ThermTech was asked to provide a more complex activated carbon system than previously supplied, with several additional challenges. The system would comprise three activated carbon vessels including all pipe work and control valves manufactured in stainless steel. The supporting structure including a complete skid unit was supplied, enabling easy assembly and mounting of the supplied equipment on-site during the installation process.

The end client, Thames Water, specified a need to select any combination of gas flow routes to any, or all, of the vessels and for each vessel to have the facility to be independently disconnected and taken offline for purging and maintenance while the plant continues operation. In this way, routine maintenance could be completed without affecting plant efficiency.

Cleaning up the Thames whilst achieving zero down-time

The solution
ThermTech designs and manufactures these activated carbon vessels, offering a range of standardised volumes as well as custom designed units. In this application, standard vessels with a volume of 4m3 met the purification and gas flow capacity requirements set out by Thames Water.
Close liaison was established with CC Jensen and the initial system concept agreed based on providing a modular style design to simplify both site installation and planned maintenance when the plant is operational. Each design stage was discussed and agreed to provide the smoothest transition from concept to final design.

H2S gas is poisonous, flammable and corrosive and in this application, pressurised. A solid engineering knowledge and fine attention to detail is required to provide a safe and reliable system when handling this gas. Material selection plays a key part in this process. Due to its excellent corrosion resistant properties, applicable in this case for the pressurised gas within the system and its external weather resistance, all pipe work, process valves and supporting structure were constructed from 316 stainless steel.

A full document package was supplied on delivery of the system to meet the client’s specifications including General Assembly (GA) and layout, Bill of Materials (BoM) and material specifications, Piping and Instrumentation Drawing (P&ID). Defined pressure performance data and pressure drop information was also provided, confirming compliance of the system to the original specifications.

Optimised design
The modular construction of the filtration plant offered a number of benefits to the project. Initially, it allowed full Factory Acceptance Testing (FAT) to be achieved before the equipment was delivered to site.

The design took into account the transportation of the equipment to the installation site and aimed to minimise the logistical costs. In addition, the modular layout minimised the installation and commissioning time, which helped to ensure the wider project was delivered on time.

The overall selection and layout of the equipment offered optimum performance with the smallest available footprint.

Steve Griffiths, Project Engineer at ThermTech, summarised: “Companies such as CC Jensen have the responsibility for the entire project and depend on trusted manufacturers like ourselves to deliver the contracted elements on time and to specification. Every project we undertake is tailored to our customer’s specifications and needs. With years of experience in designing and manufacturing filtration systems, we ensure complete integration of our systems with other processes. By delivering a turnkey solution, we can be certain of meeting every expectation of our customers.”


You must be logged in to comment

Write a comment

No comments




Sign up to view our publications

Sign up

Sign up to view our downloads

Sign up

The Magnetics Show US
22nd May 2024
United States of America The Pasadena Convention Center
2024 World Battery & Energy Storage Industry Expo (WBE)
8th August 2024
China 1st and 2nd Floor, Area A, China Import and Export Fair Complex